NORTH HEAD WRRP EMERGENCY POWER PROJECT
CLIENT: CONFLUENCE WATER
SERVICE: CONSTRUCTION OF BACKUP GENERATOR FOUNDATION & SERVICE TRENCHING
COMPLETED: MAY 2023
PROJECT OVERVIEW
Flow Industrial Group was engaged by Confluence Water to complete civil construction scope of works for installation of new diesel generator to North Head WRRP. Our scope of works included excavation, concrete construction of new generator foundation, installation of underground electrical conduits, construction of service pits with gatic lids, placement of new diesel generator and installation of handrail bollards.
Flow Industrial Group scope of works included:
Decommission, drain and remove redundant diesel generator
Remediation of existing concrete generator foundation
Bulk and detailed earthworks
Concrete construction of new generator foundation
Installation of new services pits with gatic covers
Installation of services conduits
Installation of new diesel generator
Installation of pedestrian handrail and bollards