SUEZ WATER FILTRATION PLANT
CLIENT: FITT RESOURCES
SERVICE: Excavate and construct 17 reinforced concrete pad footings
COMPLETED: NOVEMBER 2022
Flow Industrial Group was contracted by FITT Resources to excavate and construct 17 reinforced concrete pad footings at Prospect Water Filtration Plant for installation of new 316SS Lime Pipework and supports between the Lime Saturators and Lime water pump well.
The scope of work included modification and reinstallation of the reinforced concrete spoon drain ensuring stormwater is able to egress from the nearby access road.
The project was carried out successfully with no incidents within the critical 4 week work program.